99 Speed Mart: the arithmetic of opening 250 shops a year

About RM650,000 to open one outlet, with the quoted payback counting only RM300,000 of it. The filings show what the rollout really takes.

Illustration of a long row of identical shophouse shutters, standing for one shop format repeated
Illustration: Malaysia Bisnes
Compiled from public sources. Not an interview.
Company
99 Speed Mart Retail Holdings Berhad
Listed
Bursa Malaysia Main Market, 9 September 2024
Based
Selangor
Sources
Prospectus, annual report, interim reports, press releases (7)

A new 99 Speed Mart outlet takes about RM650,000 to open, and the payback of under three years that the company quotes is measured against less than half of that. Its prospectus puts set-up cost at about RM300,000 and opening stock at about RM350,000, then calculates payback on the RM300,000 alone.

Stock can be sold and a renovation cannot, so the method is defensible. But the larger cheque is the one the payback figure leaves out, and any owner pricing a second branch should write both down.

The one decision: every shop run by the company, every shop the same

The decision that shaped this chain was to stop franchising and run every outlet itself, in a single format, from rented shoplots. Franchising began in 2000 as a way to expand faster, and all franchised outlets were gone by 2010 “due to a change in our expansion strategy”, the prospectus says. It does not say what changed; the timeline below has the other dates.

The price of that choice is that each new shop’s cost sits on the group’s own books, not a franchisee’s. What it buys is a template. Its terms and its record, from the prospectus:

  • Format: a “singular outlet format”, in which only size varies.
  • Site: usually two shoplots or one corner lot of 2,000 to 3,000 sq ft, about 75% of it selling floor.
  • Tenancy: two to three years.
  • Speed: opened within one to two months of the site search starting.
  • Closures: few. The outlet table shows 740 opened and 13 closed across FY2021 to FY2023, our sum.

From one Klang sundry shop to 3,151 outlets

The record runs from a single sundry shop in Klang in 1987 to 3,151 outlets at 30 June 2026, assembled from the company’s filings, where every entry below can be checked.

  1. 1987

    Lee Thiam Wah sets up a sundry shop, Pasar Raya Hiap Hoe, in Klang. Prospectus.

  2. 1992

    He disposes of it and starts a mini-market chain, Pasar Mini 99, with 8 outlets in the Klang Valley by the late 1990s. Prospectus.

  3. 2000

    99 Speed Mart Sdn Bhd is incorporated, opens its first 99 Speedmart outlet at Batu Belah, Klang, and starts franchising. Prospectus.

  4. October 2002

    The first head office and distribution centre (DC) is commissioned at Jalan Kapar, Klang. Prospectus.

  5. 2003

    It takes over the older Pasar Mini 99 chain from Lee Thiam Wah, 8 outlets and 1 small warehouse, and rebrands the chain 99 Speedmart. Prospectus.

  6. 2008

    The 100th outlet opens at Pinggiran Batu Caves. Prospectus.

  7. 2010

    The last franchised outlets have been phased out by this year. Prospectus.

  8. 2013

    An East Malaysia company starts, with its first outlet and DC in Kota Kinabalu. Prospectus.

  9. 2017

    The 1,000th outlet opens at Shah Alam. Prospectus.

  10. 2021

    The 2,000th outlet opens at Puncak Sentul, Kuala Lumpur. Prospectus.

  11. 9 September 2024

    The company lists on the Bursa Malaysia Main Market, issuing 400.0 million new shares at RM1.65 to raise RM660.0 million. Existing holders offer a further 1,028.0 million shares at the same prospectus price, about RM1.70 billion by our calculation, so 28% of the roughly RM2.36 billion reached the company. Prospectus; Annual Report 2025.

  12. 31 December 2025

    The network stands at 3,037 outlets and 22 DCs, including 5 outlets and a small-scale DC in Fuzhou, China. Annual Report 2025.

  13. July 2026

    A DC of about 63,000 sq ft starts at Semenyih to support around 180 outlets. Interim report, 30 June 2026.

What one outlet sells, and why the average misleads

The average outlet sold about RM10,770 a day in FY2025 from roughly 500 baskets of RM21.50, which is less per day than in FY2021 even though the network grew by half, our calculation from the annual report.

99 Speed Mart: sales per outlet per day, RM
FY2021 to FY2023 as published; FY2024 and FY2025 our calculation on average outlets
99 Speed Mart: sales per outlet per day, RMAverage daily sales per 99 Speed Mart outlet fell from RM11,263 in FY2021 to about RM10,773 in FY2025, while the network grew by half.5,00010,00015,000FY2021: RM11,263RM11,263FY2021FY2022: RM10,379RM10,379FY2022FY2023: RM10,594RM10,594FY2023FY2024: RM10,284RM10,284FY2024FY2025: RM10,773RM10,773FY2025
99 Speed Mart: sales per outlet per day, RMAverage daily sales per 99 Speed Mart outlet fell from RM11,263 in FY2021 to about RM10,773 in FY2025, while the network grew by half.FY2021FY2021: RM11,263RM11,263FY2022FY2022: RM10,379RM10,379FY2023FY2023: RM10,594RM10,594FY2024FY2024: RM10,284RM10,284FY2025FY2025: RM10,773RM10,773
Chart data
YearSales per outlet per day
FY2021RM11,263
FY2022RM10,379
FY2023RM10,594
FY2024RM10,284
FY2025RM10,773
Source: 99 Speed Mart prospectus (15 August 2024) and Integrated Annual Report 2025; FY2024 and FY2025 are our calculation.
Per outlet Sales per day Transactions per day Basket
FY2021 RM11,263 459 RM24.54
FY2022 RM10,379 440 RM23.59
FY2023 RM10,594 475 RM22.29
FY2024 ~RM10,284 ~480 ~RM21.44
FY2025 ~RM10,773 ~501 RM21.50

FY2021 to FY2023 are as published in the prospectus. FY2024 and FY2025 are ours: group revenue, which includes the small 99 Bulksales e-commerce line, and transactions, divided by days and by the average of opening and closing outlets. Run on FY2023, that method gives RM10,565 against the published RM10,594, within 0.3%, and the later inputs are in the annual report and the February 2026 results release.

The shop did not get bigger; the network did. The annual report’s figures show it, on our calculations:

  • Outlets: up 50% from FY2021 to FY2025, to 3,037.
  • Revenue: up 46% over the same years, to RM11.43 billion.
  • Daily sales per outlet: down about 4%.
  • Audited group profit: RM607.3 million, about RM209,000 per average outlet, a figure that carries head office and DCs and is not a shop’s own accounts.

Two things blur the comparison. The prospectus puts the FY2021 same-store rise mainly down to demand during movement restrictions, so that year is a high base. And new outlets take three to five years to match nearby shops, it says, while net additions across FY2023 to FY2025 equal about a quarter of the network at the end of FY2025, our sum.

Where the IPO money went, and where it runs short

The RM660.0 million public issue was mostly a shop budget, and at the rate drawn so far its outlet line would cover about 598 of the 750 shops it was sized for, our projection from the interim report to 30 June 2026.

Use of the issue (share) Budget Spent by 30 June 2026 Left
New outlets (58.9%) RM389.0m RM260.4m RM128.6m
New DCs (15.2%) RM100.0m RM37.5m RM62.5m
Delivery trucks (8.3%) RM55.0m RM25.5m RM29.5m
Upgrading outlets (7.2%) RM47.6m RM36.5m RM11.1m
Repaying bank loans (6.8%) RM45.0m RM45.0m nil
Listing costs, remainder RM23.4m RM21.2m nil, with RM2.2m moved to working capital
Total RM660.0m RM426.0m RM231.7m
Show all 7Show fewer

The outlet line was built in two parts, and the draw has run higher than the plan, on the prospectus’s figures and our calculation:

  • Set-up costs: RM220.0 million, for all 750 shops.
  • Opening stock: RM169.0 million, for about 482 of them, with the remaining stock paid from internal funds.
  • Per shop: about RM519,000.
Period Drawn Net outlets added Per net outlet
Plan, 2025 to 2027 RM389.0m 750 ~RM519,000
Year to 31 December 2025 RM152.1m 259 ~RM587,000
Six months to 30 June 2026 RM65.2m 114 ~RM572,000
Money left, at the latest rate RM128.6m ~225, against 377 still planned ~RM572,000

The per-outlet figures are our calculation from utilisation balances of RM43.0 million, RM195.1 million and RM260.4 million, starting with the interim report to 31 December 2024. Treat them as a guide: stock and deposits are paid before a shop opens, net additions are not gross openings, and the filings report no deviation on this line.

So at the latest rate the money left falls short of the shops still planned. The prospectus says any shortfall falls to borrowings or internal funds, and internal funds are not the constraint, as the annual report’s cash flow statement shows:

FY2025, audited Amount
Operating cash flow RM903.3m
After lease repayments of RM179.8m RM723.4m
Opening 250 shops at RM650,000 each, our calculation RM162.5m, about 22% of the line above

The annual report says as much, describing expansion as funded largely by internally generated funds. The cash that pays for the rollout comes mainly from the shops already open, as the same report implies.

The next shops depend on where the warehouses are

The next stage of the rollout depends on warehouses, because the annual report ties a new outlet to a nearby distribution centre and says expansion will focus on the East Coast and East Malaysia. Its numbers for this stage:

  • Catchment: the group considers an estimated catchment of about 1,500 households per outlet.
  • Distance: it also considers a location within 100 kilometres’ drive of an existing DC.
  • Pace: the 2030 target of 4,250 outlets needs 1,213 more from the 31 December 2025 count, or about 243 a year, our arithmetic. So 250 is the ongoing pace and not a sprint.

The distance rule means a thin state needs a warehouse decision before it gets many shops.

State, 31 December 2025 Outlets DCs
Selangor 854 7
Johor 443 2
Sabah 266 4
Sarawak 20 1
Terengganu 13 nil
Kelantan 1 nil

Selangor holds 28% of the network on the annual report’s state map, our calculation. By 30 June 2026 the company had spent 37.5% of its DC budget against 66.9% of its outlet budget, our calculation from the table above, so that is the line to watch as the plan moves east.

What an owner can take from it

The useful part for a smaller operator is the method, which fits on one page and should be done before signing a second tenancy.

  1. Price a branch with its stock in it. Work out payback twice, on the fit-out alone and on the fit-out plus stock, and show your bank both.
  2. Write the site rule as one line with numbers. Customers in reach, and distance from wherever your stock is held. A site that fails the line does not reach the shortlist.
  3. Keep the format rigid. One layout and one size band is what lets a new shop open quickly. Every variation is a new set of drawings.
  4. Set the number of openings from cash. Multiply openings by full cost per branch, then divide by operating cash flow after rent. 99 Speed Mart’s answer is about 22%. If yours is well above 100%, you are relying on a lender, so price the loan first.
  5. Judge new and old branches separately. A rising total can hide a falling average. The prospectus names the risk plainly: an outlet opened close to an existing one can redirect its customers.

Our file on Kawan Food’s tariff year shows a different test of the same discipline: what a filing looks like when one market turns.

What the filings do not say

The documents we read leave three gaps that matter, and we have not filled them with estimates.

  1. Same-store growth. The prospectus gave 6.2% for FY2023 and 1.8% for the first quarter of 2024. We found no later figure in the results documents or the annual report.
  2. Unit costs. RM300,000 and RM350,000 are 2024 estimates, which is why the draw on IPO money is the nearest check.
  3. Closures. Recent releases give net additions or new outlets, with no closed count.

The filings behind this file

Every figure above comes from these five company documents, from the other sources listed under the article, or from our arithmetic on them, which is labelled where it appears.

  • Prospectus, 15 August 2024: unit costs, payback, outlet table, per-outlet data, use of proceeds, history.
  • Integrated Annual Report 2025: audited results and cash flow, state map, site rule, 4,250 target.
  • Interim report to 30 June 2026: 3,151 outlets, Semenyih, money spent.
  • Interim report to 31 December 2024: 2,778 outlets, money spent.
  • Results release, 13 February 2026: 259 new outlets, 532.0 million transactions, the RM21.50 basket.

Compiled from public sources. Not an interview.

Sources

  1. 99 Speed Mart Retail Holdings Berhad, Prospectus dated 15 August 2024
  2. 99 Speed Mart Retail Holdings Berhad, Integrated Annual Report 2025
  3. 99 Speed Mart, interim financial report for the quarter ended 30 June 2026
  4. 99 Speed Mart, interim financial report for the quarter ended 31 December 2024
  5. 99 Speed Mart, press release on fourth-quarter FY2025 results, 13 February 2026
  6. 99 Speed Mart, press release on second-quarter FY2026 results, 17 August 2026
  7. 99 Speed Mart, press release on second-quarter FY2025 results, 18 August 2025

Published by Malaysia Bisnes. See the masthead for who writes and who publishes this magazine.