ViTrox set a floor-space trigger for its next building. The recovery it expected came about a year late
ViTrox tied its next building to floor use, and sales turned about a year past its forecast. When half-year sales almost doubled, each extra ringgit tied up roughly 40 sen of cash, by our sums.

- Company
- ViTrox Corporation Berhad
- Listed
- Bursa Malaysia Main Market, stock code 0097
- Based
- Batu Kawan, Penang
- Sources
- Annual reports, quarterly report, sustainability report, press reports (28)
ViTrox Corporation said in public how full its factory had to be before it would build again. The recovery it expected once that building was going up came about a year late, measured by its own sales.
The 438,774 sq ft campus received its completion certificate on 18 December 2023, per the 2023 annual report. By the first half of 2026, revenue was RM641.97 million against RM324.16 million a year earlier, up 98.0%, its quarterly report shows. No filing says the building produced those sales. The company credits artificial intelligence (AI) infrastructure demand, automotive and consumer electronics markets and supply chain restructuring, and we do not claim otherwise. What the record does show is how a Penang machine vision maker decided when to build, what it got wrong, and what growth then cost in cash. Those three parts travel to much smaller companies.
The one decision: the floor-space number came before the building
ViTrox tied its next building to how full the current one was, and said so in public more than two years before construction began. In February 2019 group chief executive Chu Jenn Weng told The Star the production floor was at about 50%, would reach 70% to 80% in about two years, and that investment in the new building would start then.
Campus 3.0 was kicked off in August 2021, the 2021 annual report says. That report has operational floor space rising from 343,091 sq ft to 404,443 sq ft in the year, 83.2% of what was available at Campus 2.0. Set the opening figure against the 486,353 sq ft of usable floor in the 2023 report and 2021 began at about 70.5%, our calculation. The Star’s “production floor” may be measured differently, so this is a close fit and not a proof.
The 2019 estimate was RM200 million to RM300 million for building and equipment, The Star reported. By January 2022 the same newspaper reported RM80 million to RM100 million for the 447,000 sq ft expansion, and the 2024 report later put Campus 3.0 at “more than RM100.0 million” over 22 months. Those totals may not cover the same items.
The recovery forecast missed, and the campus went up anyway
ViTrox expected its market to turn within months, and its own sales took about a year longer than that while annual revenue fell twice. The 2022 annual report, approved on 6 April 2023, said the new space would help it capture opportunities “when the semiconductor and electronics market recovers in the next six (6) to nine (9) months”.
| Year | Revenue | Spent on property, plant, equipment | Floor in use, as reported |
|---|---|---|---|
| 2021 | RM680.12m | RM18.76m | 83.2% of Campus 2.0 |
| 2022 | RM750.25m | RM42.99m | 94.4% of Campus 2.0 |
| 2023 | RM574.92m | RM75.10m | Campus 3.0 completed in December |
| 2024 | RM552.31m | RM22.98m | 85.9% and 31.6%; 60.2% overall |
| 2025 | RM843.14m | RM37.55m | 92.4% and 43.2% |
Revenue comes from the 2025 annual report, spending from the cash flow statements in the 2021 to 2025 reports, and floor use from each year’s operations review. Where two figures appear they are Campus 2.0 then Campus 3.0, and the 2024 report says “as of now” and not year-end.
Six to nine months from that April ended by about January 2024. The first quarter to beat the same quarter a year earlier was the last of 2024, RM148.80 million against RM142.23 million, the fourth-quarter report shows, after falls in all seven quarters from the start of 2023, the earlier reports show. The forecast was about the market and this measures only ViTrox’s sales, so the yardstick is ours.
Spending peaked in the year of the sharpest fall. RM75.10 million went out in 2023 as revenue dropped 23.4% from RM750.25 million to RM574.92 million, the same reports show. ViTrox drew term loans of RM77.88 million in 2022 and RM73.15 million in 2025, and the quarterly report ties the later one to building Campus 3.0.
Chart data
| Year | revenue_rm_m |
|---|---|
| 2014 | 170 |
| 2015 | 160 |
| 2016 | 234 |
| 2017 | 327 |
| 2018 | 395 |
| 2019 | 340 |
| 2020 | 470 |
| 2021 | 680 |
| 2022 | 750 |
| 2023 | 575 |
| 2024 | 552 |
| 2025 | 843 |
On 8 July 2024, with revenue on its way to a second annual fall, work was due to start on a five-storey training and research centre under a RM45.99 million contract, according to an Edge report republished by the investment authority MIDA.
Chu told The Edge in September 2026 that “every time there’s a slowdown, after two years, we’d double our revenue”. The annual accounts mostly support him: RM18.13 million in 2009 became RM79.20 million in 2011, RM160.29 million in 2015 became RM327.49 million in 2017, and RM339.59 million in 2019 became RM680.12 million in 2021, per the financial highlights in its reports. It failed once, RM79.20 million in 2011 growing only to RM106.10 million by 2013, the same tables show, and which years count as a slowdown is our choice.
The master plan’s headline numbers remain far off
What ViTrox has built is one stage of a much larger stated plan, so the 2026 numbers should not be read as that plan delivered. The stated targets come from The Edge’s Company of the Year article of December 2021, and the 2021 annual report dates the plan 2021 to 2030.
| Measure | Stated in December 2021 | Latest record |
|---|---|---|
| Investment | More than RM2 billion | RM285.65m |
| Floor space | 2 million to 3 million sq ft | 924,171 sq ft at end-2025 |
| Workforce | 3,000 to 5,000 within five years | 959 at end-2025 |
The RM285.65 million is our sum of property, plant and equipment purchases from 2021 to June 2026 and the RM48.33 million paid for the 21-acre plot in 2021, from the cash flow statements. That is about 14% of RM2 billion, our calculation, a little over halfway through the plan’s dates. It may include items outside the plan and leaves out anything committed but unpaid. Floor space comes from the 2025 annual report and headcount from the sustainability report.
The next step is larger than the last. In September 2026 The Edge reported a 500,000 sq ft, five-storey manufacturing building due in about 15 months, and described the company as being in a “current capacity crunch”.
Almost doubling sales absorbed cash faster than profit arrived
First-half profit rose faster than revenue, but operating cash flow fell by two-thirds, which is the number a smaller company should study. Figures are from the unaudited quarterly report; the last two changes are our calculation.
| Six months to 30 June | 2025 | 2026 | Change |
|---|---|---|---|
| Revenue | RM324.16m | RM641.97m | +98.0% |
| Profit before tax | RM65.32m | RM161.61m | +147.4% |
| Net profit to owners | RM52.29m | RM136.24m | +160.5% |
| Operating cash flow | RM74.19m | RM24.16m | -67.4% |
| Spent on property, plant, equipment | RM12.43m | RM39.93m | +221.3% |
Some of the margin gain was tax. Net profit to owners went from 16.1% of revenue to 21.2%, our calculation, and tax took 16.3% of pre-tax profit against 20.8%, also ours from the same report, which cites a statutory income tax exemption at its main subsidiary.
Receivables absorbed RM145.01 million and inventories RM131.74 million, RM276.75 million together, while payables and contract liabilities gave back RM149.75 million, our sums from the cash flow statement. That leaves about RM127.00 million, or roughly 40 sen for each extra ringgit of half-year revenue, our rough calculation from the same statement.
ViTrox could carry that. Cash stood at RM368.96 million on 30 June 2026 against RM409.19 million six months earlier, with borrowings of RM82.24 million at rates of 4.73% to 4.77%, the report shows.
Floor space took half the first public money, long before any trigger
About half of what ViTrox raised at its 2005 listing went on floor space, and its later move between Bursa boards raised nothing. The listing raised RM10.56 million, of which RM5.35 million, half by our calculation, repaid financing for land and three factory buildings, per the 2006 report. ViTrox transferred to the Main Market on 9 November 2009, a year when revenue fell 31% to RM18.13 million and it issued no shares, the 2009 annual report shows.
- 1998
Chu Jenn Weng and Steven Siaw Kok Tong leave Hewlett-Packard in Penang and start in a rented bedroom with RM20,000 borrowed from family and friends. The Edge, December 2021.
- 2000
With Yeoh Shih Hoong on board, the three establish ViTrox. The Edge, December 2021.
- 24 June 2004
Converted into a public limited company. Company background page.
- September 2005
Lists on Mesdaq, now the ACE Market, raising RM10.56 million. The Edge, September 2026; Annual Report 2006.
- 9 November 2009
Transfers to the Main Market. Annual Report 2009.
- 9 December 2014
Buys 22.2 acres at Batu Kawan for RM34.2 million. Annual Report 2014.
- 27 October 2015
Breaks ground on Campus 2.0, then 450,000 sq ft. Annual Report 2015.
- February 2019
Chief executive names the 70% to 80% floor-use point for the next building. The Star.
- May 2021
Announces the purchase of about 21 acres for RM48.3 million under a plan to 2030. Annual Report 2021.
- 6 April 2023
Board approves the report forecasting a market recovery in six to nine months. Annual Report 2022.
- 18 December 2023
Campus 3.0 receives its completion certificate. Annual Report 2023.
- Fourth quarter 2024
First quarter since the forecast with revenue above the same quarter a year earlier. Quarterly report.
- September 2026
A 500,000 sq ft manufacturing building is reported, due in about 15 months. The Edge.
What an owner can take from it
Most of this can be copied without a listing, starting with writing down the number that would make you build the next thing.
Name the trigger before you need it. Pick the utilisation of your floor, machines or people that starts the next investment, and tell your board or banker.
Assume the recovery comes late. ViTrox’s six to nine months ran about a year over, our reading of its quarterly reports. Test whether your repayments survive a 23% fall in sales for two years, the size of ViTrox’s first drop in its annual reports.
Separate the shell from the fit-out. Campus 3.0 finished in 2023, yet the 2025 report still had 22.5% of it under renovation for later expansions. Fit out when orders arrive and you defer part of the bill.
Budget cash for growth, not only for space. Use your own debtor and stock days. At ViTrox’s rough 40 sen, our figure above, a firm adding RM2 million of sales would tie up RM800,000.
ViTrox spent about 11% of 2025 revenue on R&D, the annual report says, and sells capital equipment, so copy the method and not the ratios.
What the record leaves open
The quarterly report to 30 June 2026 and the other documents we read give no third-quarter 2026 result, current floor use or 2026 headcount. Nor do we know how much first-half revenue came from the newer space. We have not spoken to the company.
The filings behind these figures
Each figure comes from these documents, from the others listed under this article, or from our labelled arithmetic. Corrections go to our corrections page.
- Quarterly report to 30 June 2026: half-year results, cash flow, borrowings.
- Annual Report 2025: five-year revenue, floor space, in-use rates.
- Annual Report 2021: master plan dates, land, Campus 3.0 start.
- The Star, 25 February 2019: the 70% to 80% trigger and first cost estimate.
- The Edge, December 2021: founders and the plan’s stated targets.
Compiled from public sources. Not an interview.
Sources
- ViTrox Corporation Berhad, quarterly report for the quarter ended 30 June 2026
- ViTrox Corporation Berhad, quarterly report for the quarter ended 31 December 2024
- ViTrox Corporation Berhad, quarterly report for the quarter ended 30 September 2024
- ViTrox Corporation Berhad, quarterly report for the quarter ended 30 June 2024
- ViTrox Corporation Berhad, quarterly report for the quarter ended 31 March 2024
- ViTrox Corporation Berhad, quarterly report for the quarter ended 31 December 2023
- ViTrox Corporation Berhad, quarterly report for the quarter ended 30 September 2023
- ViTrox Corporation Berhad, quarterly report for the quarter ended 30 June 2023
- ViTrox Corporation Berhad, quarterly report for the quarter ended 31 March 2023
- ViTrox Corporation Berhad, Annual Report 2025
- ViTrox Corporation Berhad, Sustainability Report 2025
- ViTrox Corporation Berhad, Annual Report 2024
- ViTrox Corporation Berhad, Annual Report 2023
- ViTrox Corporation Berhad, Annual Report 2022
- ViTrox Corporation Berhad, Annual Report 2021
- ViTrox Corporation Berhad, Annual Report 2018
- ViTrox Corporation Berhad, Annual Report 2015
- ViTrox Corporation Berhad, Annual Report 2014
- ViTrox Corporation Berhad, Annual Report 2009
- ViTrox Corporation Berhad, Annual Report 2006
- ViTrox, financial quarterly reports page
- ViTrox, company background page
- The Star, Vitrox plans to invest up to RM300mil on Batu Kawan facility, 25 February 2019
- The Star, Vitrox to invest up to RM100mil in expansion, 10 January 2022
- The Star, ViTrox anticipates favourable 2H26 outlook, 30 July 2026
- The Edge Malaysia Weekly, Company of the Year: ViTrox Corp Bhd, 27 December 2021 to 2 January 2022
- The Edge Malaysia Weekly, ViTrox rides AI-fuelled complexity to new highs, 21 to 27 September 2026
- The Edge Malaysia, via the Malaysian Investment Development Authority, RM46 million contract award to SIB, 1 July 2024
Published by Malaysia Bisnes. See the masthead for who writes and who publishes this magazine.
See something wrong? Write to the editor through the corrections page. Corrections are noted on the article. A company may also ask for a correction there, with a public source.